Project timeline

Below is a timeline for the Risk Assessment Workflow project. If you want to get in touch with the team please email the Health and Safety team at health.and.safety@lse.ac.uk.

A table with project stages and the timeframes they're due to be complete
July/August 22  Project close
June/July 22  Handover to BAU
May 22  Initial Go Live
April/May 22  User Training
April 22  UAT
April 22  Training for UAT
November 21 - April 22  System Testing
October 21  Build / Config
September 21  Supplier Contracting
August 21  Portfolio Board
July 21  Requirements, Supplier Selection, full business case
June 21  Portfolio Board Decision
May 21  Requirements Gathering
April 21 Project Kick Off