Estates News Updates

Road closure during Graduation ceremonies 16 - 19 December 2024

Portugal Street will be closed to traffic for the duration of the Graduation ceremonies 16 - 19 December 2024 from 8am to 8pm.

Please see the traffic management plan detailing the diversion route below. 

Diversion Route Plan - Portugal Street Graduation 2024

Please note, there will be limited access to Gorger Alley and a parking bay suspension on Portugal Street (Beside Peacock Theatre).

Campus Longitudinal Study on Students’ Views of the Estate

What do students think about the Estate? Evolving LSE's campus to meet students' needs

Studies on student perceptions of campus quality were undertaken in 2011, 2015, 2019 and 2023, and in 2012 research on what student aspirations for campus study space, were undertaken. Find out how the School addressed the complex challenge of evolving the campus to meet students' wants and needs.

Campus cycle rack survey

As part of the Bankside House redevelopment planning application we are required to undertake a survey of the usage of cycle racks on campus.  This will involve installing temporary cameras that will monitor usage of all campus cycle storage for approximately one week.

The cameras will be installed on Thursday 28 November and removed on Friday 6 December 2024.  Signage will be installed at each point to make everyone aware of the cameras and their purpose.

If you have any questions please contact Stuart Pennycook at: s.pennycook@lse.ac.uk

King's Chambers finial works

These works will not commence on 28 October, as planned.  Once a start date has been agreed this will be communicated.  Apologies for any inconvenience.

George IV envelope remedial works 29 July - December 2024

Essential roofing and building fabric work to George IV Building will commence on 29 July 2024. Due to unforseen works during construction, the completion date will now be 13 December 2024.

To ensure the safety of students and staff passing through this area, the contractor will put out safety barriers around the working area when they are putting up and taking down the scaffolding.

George IV Pub will continue trading throughout the construction programme and their opening hours will not be affected by the construction works.

George IV Building Envelope 2024
Map of scaffold enclosure

We apologise for any inconvenience caused during these essential maintenance works.

If you have any further queries or problems, please contact: d.mcpherson1@lse.ac.uk 

Temporary diversion on Clement's Inn 8 - 12 July 2024

Due to roof works at 265 Strand, Clement's Inn will close at Strand end (access will be via CBG steps) 8 - 11 July (4pm-10pm) and possibly 12 July, 4pm-10pm (if weather delays occur).

Please use the alternative route during this time:

Clements Inn Route closure map with assembly June July 2024
Alternative route to/from Clement's Inn during closure period

The fire assembly point for Clement House occupants will be outside the Garrick during this time. 

Decarbonisation project to commence in LRB and CON

Back in February 2024, LSE received £2.7m of funding from Salix.  As reported, these funds will be used to take a whole building retrofit approach to the decarbonisation of two campus buildings: Connaught House (CON) and Lionel Robbins Building (LRB).

Find out more about the project that will start soon and is estimated to complete in Winter 2025. 

Old Curiosity Shop wins RICS award

The Old Curiosity Shop has been awarded winner in the RICS Regional Awards 2024 category of Heritage Project for the London region.  The project was one of 9 London projects shortlisted for the regional award. 
Congratulations to Barbara Moldawa from our Capital Development team, who led the project for LSE Estates.
Read more about the awards here

 

Old Curiosity Shop
RICS Certificate awarded to The Old Curiosity Shop

Lincoln's Inn Fields road closure Sat 8 - Sun 9 June 2024

A tower crane is due to be installed at 35 Lincoln’s Inn Fields (elevation facing the Sir Arthur Lewis Building, SAL) on the weekend of 8 – 9 June 2024 which will involve a road closure to part of Lincoln Inn Fields (LIF). The map below illustrates the extent of the roads and parking bays that will be affected during the erection of the tower crane. Notices have been posted on lampposts in the area advising of the road closures.

Road closure LIF June 2024
Plan showing closures during tower crane lift

The closures will commence on Saturday 8 June from 6:00am and roads will reopen on Sunday 9 June at 8.00pm. The contractor has provided the following programme of activities for the weekend.

Description

Start

Date

Finish

Date

Road closure of LIF between Serle Street and Portsmouth Street

6am

08/06/24

8pm

09/06/24

Parking bays on LIF adjacent to 35 Lincoln Inn Fields suspended

6am

08/06/24

8pm

09/06/24

Mobile crane in place to prepare for the tower crane installation

8am

08/06/24

10am

08/06/24

Tower crane delivered in 9 sections throughout the day on the back of articulated lorries

10am

08/06/24

1pm

09/06/24

Tower crane installation

10am

08/06/24

1pm

09/06/24

Read more about the Firoz Lalji Global Hub Redevelopment Project and, more specifically, find out how the demolition works may impact you.

Temporary diversion on Clement's Inn 6 May - 3 June 2024

Due to scaffolding removal at 265 Strand, Clement's Inn will close each evening from 5-11pm (6-11pm during exams in CLM and PAN) from 6 May - 3 June 2024.

Please use the alternative route during this time:

The fire assembly point for Clement House occupants will be outside the Garrick during this time. 

Clements Inn Route closure map with assembly 2024
Map shows alternative route during closure of Clement's Inn

 

Clare Market closure on Saturday 13 April - 8am - 5pm

Access via Clare Market will be closed on Saturday 13 April from 8am - 5pm to facilitate a crane lift.

Please use St Clement's Lane during this time.

We apologise for any inconvenience this may cause.

Clare Market Crane Lift logistics
Image showing where barriers will be erected during the closure

Old Building and St. Clement's shutdown

As part of the Old Building Refurbishment and Electrification Project, some essential electrical works necessitate building closures and power shutdown to OLD and STC. This work will also require DTS Services to run at risk for Campus and Residential Services:

DTS services will be running at risk on the following dates:

Saturday 23 March 8am to 9am

Tuesday 2 April 9am to 5pm

Details of when and where these works will take place:

St Clements 

  • Saturday 23 March 8am – 9am power shutdown within STC
  • Tuesday 2 April STC closed

Old Building

  • Wednesday 3 April and Thursday 4 April 
    OLD will have power outages from 8:30am – 6.30pm (OLD to CON access via 2nd floor link bridge will be maintained)
  • Local power circuits and heating and ventilation systems may also be affected in these areas.
  • These works have been planned during the Easter closure period to minimise the impact on building occupants.  Thank you for your cooperation.
  • Saturday 13 April Clare Market closed 8am – 5pm to facilitate crane lift. 

For more information about the project, see the latest newsletter.

Portsmouth Street, partial closure 10 Feb 2024

There will be a partial road closure and pedestrian diversion on Portsmouth Street (between Coopers Restaurant and Angelo's Barber Shop) between 9am and 4pm on Saturday 10 February 2024.  This is due to crane operations, carrying out roof repairs at 50 Lincoln's Inn Fields. See plan for exact location.

 

50L roof repairs 2024 02 10
Plan of Portsmouth Street partial road closure on 10 Feb 2024

 

 

Clare Market scaffolding removal 4 - 8 December 2023

As part of the Old Building Refurbishment works, scaffolding in Clare Market will be removed from Monday 4 December to Friday 8 December 2023.

A lorry will be parked in Clare Market as indicated on the logistics plan.

Barriers will segregate the works area from the pedestrian route.

Pedestrian access to the nearby buildings will be unaffected and pedestrians will still be able to go through Clare Market.

Thank you for your cooperaton during these works.

Planning application submitted for 35L project

Find out the latest on the Firoz Lalji Global Hub project at 35 Lincoln's Inn Fields.

A Public Exhibition will be held in the Marshall Building 31 October - 17 November 2023 showing the updated submission.

Come along to the next Town Hall meeting on Monday 6 November 12:00 - 1pm in the Shaw Library to find out more.

20 Kingsway pavement light improvement works

Pavement light improvement works to 20 Kingsway will commence on 30 October and complete by 3 November 2023.  

These works will include noisy works, which will take place between 8am - 10am each day. It is our intended target to complete noisy works no later than 10am each day making every attempt to ensure this. We will make best endeavours to reduce any noisy impact during reading week.

Entrance to 20 Kingsway will not be affected during the works but please be mindful that access on the pavement in front of 20 Kingsway will be reduced slightly due to the works.

To ensure the safety of students and staff passing through this area, the contractor will put out safety barriers around the working area. 

Staff News 2023 10 24
Area affected by pavement light improvement works outside 20 Kingsway

We apologise for any inconvenience caused during these works.

If you have any queries or problems pleas contact: d.mcpherson1@lse.ac.uk

Old Building Refurbishment Project update

Find out how the project is progressing in the October newsletter (pdf)

Introducing the Estates Division Building Managers

As a result of customer feedback, LSE Estates Division has appointed five Building Managers to be the primary point of contact on Estates related issues for Departments, Research Centres and Divisions.  Find out who the appointed Building Manager is for your building and how to contact them.

Old Building refurbishment project update

Works are progressing on the Old Building refurbishment project.  The link bridge between Old Building and St. Clement's has now been removed.  As part of the refurbishment some toilet facilties are currently out of action.  Check out the September 2023 newsletter (pdf) or visit the project page for further information.

Clare Market closure 29 August - 2 September 2023

Works to remove the OLD/STC link bridge will complete on 26 August 2023.
The scaffolding will be removed between 29 August and 2 September 2023.Clare Market will be closed during this period, please use alternative routes as shown on the map (pdf).

More information about the Old Building Refurbishment project can be found on the latest newletter.

 

Clare Market closure map V9 2023 08 29
campus map showing alternative routes during Clare Market closure

 

Clare Market closure 29 July and 2 August 2023

Works to erect scaffolding to enable the removal of the OLD/STC link bridge continue to affect Clare Market access.  The route will be closed to pedestrians on Saturday 29 July and again on Wednesday 2 August 2023.  During these periods please use alternative routes, as shown on the map (pdf).  Information about the Old Building refurbishment project can be found here.

Clare Market closure map V8 29 July & 2 August web
Map showing alternative route during closure Clare Market

Clare Market closure 24 - 26 July 2023

Due to scaffold erection, ahead of the removal of the link bridge between Old Building and St Clement's, Clare Market will be closed to pedestrians from Monday 24 - Wednesday 26 July inclusive.

We apologise for any inconvenience this may cause, please use the alternative routes during this period, as shown on campus map (pdf).

23_0443 Clare Market closure map V3 web
campus map showing alternative routes during Clare Market closure

 

Temporary diversion on Clement's Inn 10 - 30 July 2023

Due to scaffolding erection at 265 Strand, Clement's Inn will close each evening from 5-11pm from 10 - 30 July 2023.

Please use the alternative route during this time:

The fire assembly point for Clement House occupants will be outside the Garrick during this time.

23_0420 Clement's Inn closure map V6 web
Map showing alternative route during closure of Clement's Inn

 

Electrification of the Cheng Kin Ku Building

Road closures 25 - 26 March 2023

A crane lift is planned in the New Academic Building for weekend 25-26 March 2023. Lincoln's Inn Fields and Sardinia Street will be closed at times to faciliate this, see the closure schedule below:

NAB Exclusion Zones March 2023
Exclusion zone whilst crane is in operation
NAB road closures March 2023 crop
Road closure plan for 25-26 March 2023

Old Building Refurbishment and Electrification

Works are progressing on the Old Building refurbishment project.  Check out the July 2023 newsletter (pdf) or visit the project page for further information.

The Old Building (OLD) is about to undergo some long-awaited refurbishment works.  Occupants are being moved into alternative accommodation whilst these works take place. Find out more about the project here or read the newsletter (pdf)

Old Building link bridge stone repairs

03 April to mid May 2023

Building fabric improvement work to Old Building will commence on 03 April and complete in mid May 2023.

Ramp access to the main entrance will be out of service from 3 - 7 April and 1 - 5 May as noted on the diagram below, there is alternative ramp access via the Student’s Services Centre in Clare Market.

To ensure the safety of students and staff passing through this area, the contractor will put out safety barriers around the working area when they are putting up and taking down the scaffolding. 

23_0174 Old Building Link Bridge Stone Repair - Poster A3 V3
map of affected area

We apologise for any inconvenience caused during these building fabric improvement works.

If you have any further queries or problems, please contact: d.mcpherson1@lse.ac.uk.

King's Chambers works

03 April to mid August 2023

Essential roofing and building fabric work to King’s Chambers will commence on 03 April and complete in mid August 2023.

To ensure the safety of students and staff passing through this area, the contractor will put out safety barriers around the working area when they are putting up and taking down the scaffolding.

Ye Old White Horse Pub will continue trading throughout the construction programme and their opening hours will not be affected by the construction works.

23_0176 King's Chambers Building Envelope - Poster A3 V2
map of affected area

We apologise for any inconvenience caused during these essential maintenance works.

If you have any further queries or problems, please contact: d.mcpherson1@lse.ac.uk.

 

LSE campus development recognised

LSE Campus has been awarded the Irene Barclay Prize at the Open City Stewardship Awards in respect of our long term strategy for the development and care for our campus. Visit Open City for more information.

LSE appeared on the front cover of the Sept/Oct 2022 edition of Architecture Today which featured a 24 page retrospective on the development of the LSE Estate. 

 

Campus buildings condition surveys

12 September - 5 December 2022

The Estates Division continues to maintain and improve both residential and campus accommodation in accordance with the Long Term Maintenance (LTM) programme.  The current 10 Year LTM programme to all sites was established from a series of condition surveys last undertaken in 2017. Historically the condition surveys are renewed on a five-year cycle. The current programme is now in its fifth year and is becoming out-of-date and inaccurate.  

NIFES Consulting Group have been appointed to undertake the condition surveys and a review of the LSE’s asset register.  The surveyors who will be on site are: Lee Brown, Ben Coddington, Peter Brown, Reiss Livesey.

The campus surveys will commence on Monday 12 September 2022 and should be completed by 5 December 2022.

General hours of working will be 8am to 6pm Monday to Friday, however earlier times may be adopted to access teaching rooms.  To enable maximum flexibility for accessing all areas in all buildings NIFES have not been tied to a building-by-building programme.

NIFES will need access to all areas on campus to enable an accurate and useful survey to be produced, the surveys are visual and should have minimum impact on building occupants.  For restricted areas on campus, such as comms rooms and security rooms, access will be requested and agreed directly with the relevant department.

Thank you for your co-operation.

If you have any questions please contact Emma Lovegrove e.j.lovegrove@lse.ac.uk  

9-10 Sheffield Street & Ye Old White Horse Pub Roofing Works

18 April to early August 2022

Essential roofing work to 9-10 Sheffield Street and Ye Old White Horse Pub will commence on 18 April 2022 and complete in early August 2022.

To ensure the safety of students and staff passing through this area, the contractor will put out safety barriers when they are putting up and taking down the scaffolding, as noted in green (clearance zone) on the diagram below.

Ye Old White Horse Pub will continue trading throughout the construction programme and their opening hours will not be affected by the construction works.

22_0207 9-10 Sheffield Street_white Horse Works A3 POSTER
map showing affected area

We apologise for any inconvenience caused during these essential maintenance works.

If you have any further queries or problems, please contact: d.mcpherson1@lse.ac.uk.

Lincoln's Inn Fields carriageway resurfacing

Lincoln's Inn Fields will be closed between Portsmouth Street and Serle Street (32L to Coopers Restaurant) from Monday 11 to Wednesday 13 April 2022.  This is to facilitate the resurfacing of the carriageway, which is being carried out by F.M. Conway Ltd on behalf of Westminster City Council.  Pedestrian access to properties will be maintained at all times.

Power outage 17 January 2022

Monday 28 February 2022

We are pleased to announce that following the power outage on 17 January 2022 all issues have now been resolved.

Friday 4 February 2022

We are still experiencing issues with some lifts, following the power outage on 17 January 2022

Marshall Building (MAR)

  • Lift 130 is currently out of service due to damaged safety edges.  These parts should be fitted on Friday 4 February.

Saw Swee Hock Student Centre (SAW)

  • Right hand lift is still currently out of service, once parts are delivered they will be fitted and the lift tested.

Friday 28 January 2022

Since the 17 January there have been issues across campus where mains network power surges have had an impact on LSE buildings. We have been working to resolved these issues.

We have set out below the status of each building:

Connaught House (CON)

  • This lift is now working and back in service.

Lionel Robbins Building (LRB)

  • This lift is now working and back in service.

Marshall Building (MAR)

  • Lift 130 is currently out of service due to damaged safety edges.  These parts have now been ordered and once site they will be fitted.

Saw Swee Hock Student Centre (SAW)

  • The manufacturer has attended site and tests have revealed that further components are required.  Currently there is a limited supply of the required parts and only 1 part was available. This has been fitted on the left hand lift and this lift is currently back in service.  The part for the right hand lift should be on site early next week and once delivered will be fitted and the lift tested.
    You can still use the alternative lift which will give you access to the basement up to the 5th floor.

Friday 21 January 2022

Since the 17 January there have been issues across campus where mains network power surges have had an impact on LSE buildings. 

Maintenance have been liaising with UK Power Network (UKPN) daily and are reporting all these issues to them and liaising with their engineers.  The UKPN engineer has investigated the problem and has identified the HV voltage is running high during times of low demand e.g., early mornings or late evenings which is believed to be causing the power surges.

Whilst we continue our discussions with UKPN, a lift engineer is on standby on campus between 7:00 am and 8:00 am (high risk period) to assist with immediate passenger release should the lifts fail. 

We have set out below the status of each building:

Connaught House (CON)

  • the power surges are causing a lift failure which means that the lift stops and goes out of service.  Currently we are resetting the lift as required as we continue our discussions with UKPN.

Lionel Robbins Building (LRB)

  • the power surges are causing a lift failure which means that the lift stops and goes out of service.  Currently we are resetting the lift as required as we continue our discussions with UKPN.

Marshall Building (MAR)

  • Through consultation with the lift installers and engineers we have made some adjustments which seem to have stabilised the issues. 

Saw Swee Hock Student Centre (SAW)

  • the power surge has damaged component parts within the 2 main lifts.   Parts have been fitted but we are waiting for the attendance of the manufacturer to recommission the lifts before returning back to service.  Please use the alternative lift which will give you access from the basement up to the 5th floor.

Thursday 20 January 2022

Following the power surge on Monday morning, the following issues are still ongoing.

Connaught House (CON)

  • This lift is currently out of service.  We are waiting for a specialist to investigate an intermittent fault which has developed on the lift since the power surge.

Marshall Building (MAR)

  • The issues in this building have stabilised.  Should anyone experience any issues please email Estates-Help-Desk@lse.ac.uk  or call the Estates Helpdesk x2444

Saw Swee Hock Student Centre (SAW)

  • the power surge has damaged component parts within the 2 main lifts.  Parts have been fitted but we are waiting for the attendance of the manufacturer to recommission the lifts before returning back in service.

Wednesday 19 January 2022

Following the power surge on Monday morning, the following issues are still ongoing. We will provide a further update by the end of the week.

Connaught House (CON)

  • The power surges are causing a lift failure which means that the lift returns to ground floor and goes out of service.  Currently we are resetting the lift as required as we continue our discussions with UKPN.

Marshall Building (MAR)

  • 4pm update: the power surges are causing a lift failure which means that the lift stops and anyone using the lifts will activate the lift alarm within the lift car to alert the building security who have arranged for passengers to be released.  Whilst we continue our discussions with UKPN, a lift engineer is on standby on campus between 7:00 am and 8:00 am (high risk period) to assist with immediate passenger release should the lifts fail.  To mitigate the impact of future power surges to the lifts we are investigating solution with the installers.
  • 3 lifts currently out of order. This is being dealt with by the lift contractors and updates will follow

Saw Swee Hock Student Centre (SAW)

  • 4pm update: the power surge has damaged component parts within the 2 main lifts.  Parts are being replaced and we hope to have these lifts back in operation as soon as is possible.
  • 2 lifts still out of service due to replacement parts needed but all other lifts can be used as an alternative

Tuesday 18 January 2022

Following the power surge yesterday morning, the following issues are still ongoing, next update Wednesday 19 January at 10am.

Connaught House (CON)

  • 3pm update: lift is now back up and running (Resolved)
  • 1pm update: Lift out of service, engineer on site. (Ongoing)

Marshall Building (MAR)

  • 1pm update: all 4 lifts are now working (Resolved)
  • currently 1 lift out of service.  The lift company is currently on site and has shut down all the lifts while they test for any issues and will put the lifts back in service once they are happy all lifts are safe. (Resolved)

(The electrical spike affected the fire alarm panel in MAR which has caused an issue with the lifts.  Both the lift contractor and fire alarm contractor are on site and are dealing with this issue.  We will provide further updates once they have done their inspections). 

Saw Swee Hock Student Centre (SAW) 

  • 3pm update: 2 lifts still out of service due to replacement parts needed, the firefighting lift can be used as an alternative.(Ongoing)
  • 1pm update: 2 lifts still out of service (Ongoing
  • 2 lifts still out of service due to replacement parts needed, the firefighting lift can be used as an alternative.(Ongoing)

Monday 17 January 2022

Early this morning, the Estates team were made aware of a number of power issues across the School campus which appear to have been caused by a power surge. As a result, buildings across campus are experiencing issues in areas such as lifts, power sockets, and in some cases boilers not working.

We will provide further updates throughout the day, next update Tuesday 18 January at 10am.

The following buildings/areas have been affected (link to campus map):

Centre Building (CBG)

  • 12 noon update: power restored to 2nd floor (Resolved)
  • no power to 2nd floor rooms (Ongoing)

Connaught House (CON)

  • 2.30pm update: lifts back in service (Resolved)
  • 12 noon update: lifts out of service (Ongoing)

Cowdray House (COW)

  • 2.30pm update: lifts back in service (Resolved)
  • 12 noon update: lifts out of service (Ongoing)

32 Lincoln's Inn Fields (32L)

  • 12 noon update: lifts back in service (Resolved)
  • 2 lifts out of service (Ongoing) 

Lionel Robbins Building (LRB)

  • 12 noon update: no power to 3rd floor (Ongoing)
  • no power on ground floor (Ongoing)

Marshall Building (MAR)

  • All lifts were affected, currently 1 lift still out of service (Partially resolved)

Saw Swee Hock Student Centre (SAW) 

  • 12 noon update: power restored to Faith Centre (Resolved)
  • no power to Faith Centre (Ongoing)

  • 12 noon update: 2 lifts still out but customers can use the firefighting lift (Ongoing)
  • 2 lifts out of service (Ongoing)

  • 4pm update: hot water reinstated (Resolved)
  • No hot water (Ongoing) 

We are working through issues as soon as we are made aware of them – in most cases, this is a matter of resetting the service.

UK Power Networks are investigating the cause of the power outage.

If you do have any issues please report these to the Estates Helpdesk

Emergency or urgent Estates issues
Call 020 7955 2444 or 020 7955 6244

Non-urgent Estates issues
Call 020 7955 7956

Staff can also report faults by using the self-service portal  

 

LSE becomes the first Carbon Neutral verified university in the UK

In a first for UK higher education, the London School of Economics and Political Science has been independently verified as carbon neutral for the academic year 2020/21, for all its measured emissions.

Find out more about how this was achieved....

This exciting news was covered by the BBC and featured in the Times Higher Education news (pdf)

Additional cycle stands on campus

Additional provision of cycle stands will be installed by Westminster Council across the Campus during the period from 1st June and 18th June. 

The works will be carried out by a contractor employed directly by Westminster Council. 

A plan of the affected locations is attached (blue dots).

Please  note that the works will involve drilling and there maybe noise at times.

Indicative dates for the works have been advised as follows:

Please note that these dates may be subject to change, dependent on weather conditions and resource availability.

The aim is to complete the installation of all cycle stand by 18th June, before the start of the summer school.

Location Ref

Location

Start Date

End Date

Duration

No of Stands.

 

J

Sheffield St. North

07/06/2021

07/06/2021

1 Days

10

Completed

I

Sheffield St. South

08/06/2021

08/06/2021

1 Day

9

Completed

K

Sardinia Street

09/06/2021

09/06/2021

0.5 Days

3

 

H

Portugal Street

10/06/2021

11/06/2021

2 Days

9

 

E

Carey Street

14/06/2021

14/06/2021

0.5 Days

0

 

D

Grange Court

15/06/2021

16/06/2021

2 Days

15

 

M

New Inn Passage  (outer)

17/06/2021

17/06/2021

1 Day

3

 

N

New Inn Passage (inner)

4

 

additional external cycle stands 2021
Potential locations for additional external cycle stands (blue dots)

 

If you have any queries or problems please contact:  f.biancelli@lse.ac.uk 

 

Clement's Inn gate/stair closure

April update - closure delayed until 22 - 25 April 2021

The reinstallation of the gate was unfortunately delayed.

These works will now take place between 22 - 25 April 2021.

During this time the stairs will not be accessible, please follow the diversion route. 

If you require access to the lift during this time please email:  d.mcpherson1@lse.ac.uk giving sufficient time for the contractor to facilitate access.

21_0066 Campus Map Clements Inn Gate closure
Diversion route during closure 22 - 25 April 2021

Clements Inn gate modifications – 15 March 2021 to mid April 2021

Works to increase accessibility to the gate at the top of Clement's Inn stairs will commence on 15 March 2021.

The contractor will temporarily close the area to undertake the removal and later the reinstall of the gate for minimal disruption. 

There will be two closure periods 15 March - 21 March and 12 April - 14 April.

The works should be completed before all campus buildings reopen in April 2021.

Please follow the diversion during the closure period (see map below).

If you require access to the lift during this time please email:  d.mcpherson1@lse.ac.uk giving sufficient time for the contractor to facilitate access.

We apologise for any inconvenience caused during these works.

 

21_0066 Campus Maps 800px
Alternative routes during gate closure

 

Student Services Centre ramp closure

Pedestrian access along Clare Market will re-open on Monday 20 January.

In order to progress the landscaping works the ramped access on Clare Market, up to the Student Services Centre (SSC), will be closed with effect from Saturday 25 January until late February.

The accessible route into the main entrance of the Old Building will remain open throughout this period and signs put in place to show alternative routes into SSC.

SSC ramp closure 2020 01 25 red
Alternative route into OLD Building

 

We apologise for any inconvenience caused by these works.

 

Landscaping update December 2019

Remaining tree planters – early December 2019

The final three planters to be constructed to the western edge of the new square are almost complete.  The planters match those to the front of the Plaza Café. The hoarding currently surrounding the planters will be removed by 1 December. The trees will then be delivered and planted on the 2 December. There may still be some isolated pockets of works to complete the square throughout early December.

Resurfacing of Clare Market – December 2019 to early April 2020

You may have noticed that following 4 years of construction traffic, Clare Market is looking slightly worse for wear. Works to re-surface Clare Market will commence on 9 December. The 5 week holiday period will allow the contractor to undertake all the noisiest most disruptive works while the Campus is at its quietest and there is no teaching taking place. The intent is to have all the heavy breaking and the new concrete sub-base laid in advance of students returning to the School on 20 January 2020. The contractor is aware of graduation ceremonies w/c 16 December and LSE examinations taking place w/c 13 January and will avoid disruptive activities during this period.

Clare Market will be completely closed to vehicles and pedestrians until 19 January.  Diversion routes, including fire evacuation for Centre Building, will be via St Clement's Lane or Old Building, see map (pdf).

Clare Market Closed Pedestrian Routes-web
Alternative route during Clare Market closure

Works to re-surface Clare Market will then continue from late January to early April 2020. During this period pedestrian routes will be opened up on Clare Market to ensure that connectivity across campus is not too adversely impacted by these works. There will be some unavoidable noisy works within this period,  the contractor has been instructed to mitigate this as far as possible through the use of acoustic enclosures.

Once complete, Clare Market will mirror Houghton Street and the new public square, creating a real sense of place in the heart of the campus.

Art Installation – early January 2020

In line with the planning requirement for public art, Artist Tod Hanson has been commissioned to design a mural for the St Clement’s wall. An art installation contractor will now commence applying the mural to the wall in early January 2020, with the works taking circa 3 weeks to complete, depending on the weather.

We thank you for your patience and understanding.  Should you have any queries regarding the above please contact Estates.Centrebuildings@lse.ac.uk 

St Clement's Lane access restricted from 16 May 2019

St Clement's Lane will have limited pedestrian access from Thursday 16 May 2019 to enable landscaping works.  Please use the diversion route around the Library, as per map below.

19_0090 Clements-Lane-Closed Pedestrian Route-A1_v3-MAPONLY
Diversion route around LRB during closure of St Clement's Lane

 

OLD building ramp closed until 24 May 2019

Due to unforeseen complexities the landscaping works in Houghton Street are still ongoing.  The accessible access into OLD building main entrance will remain closed until 24 May.  Please continue to use the ramp on Clare Market into the Student Services Centre during this period.  We apologise for the inconvenience caused.

Grange Court works were completed on schedule and this route is now open.

ramp-closure-18_0912 Pedestrian Route-A1_v2-MAPONLYjpg
Alternate route for accessible entry into OLD building during landscaping works

 

Grange Court closed 1 April - 7 May 2019

Grange Court will be closed from 1 April until 7 May to enable Mace to undertake the next phase of the Centre Buildings landscaping works.  Access to and from Fawcett, Pankhurst and Pethick-Lawrence Houses will be via the Aldwych during this period.

Pedestrian Map-Key large
Campus map showing alternative routes duirng Grange Court closure

 

Public Square 2 B web
View of LSE Square, showing walkway through to Grange Court

 

Route restrictions around campus Jan - Mar 2019

Closure of ramp to Old Building main entrance 

4 February – 30 April 2019

Ramp access to the main entrance of the Old Building will be temporarily closed whilst essential works are undertaken in this location.

Those requiring ramped access to the Old Building should use the ramp on Clare Market into the Student Services Centre during this period.  

ramp-closure-18_0912 Pedestrian Route-A1_v2-MAPONLYjpg
Alternate route for accessible entry into OLD building during landscaping works

St Clement's Lane has now reopened

Thank you for your patience during the UKPN works.

St Clement's Lane closed

6 - 17 February 2019

The end of St Clement's Lane has been closed to enable UKPN to undertake works to their network sub-station.  Please use the diversion route around the Library, as per map below.

19_0090 Clements-Lane-Closed Pedestrian Route-A1_v3-MAPONLY
Diversion route around LRB during closure of St Clement's Lane

 

Pavement closure Lincoln's Inn Fields

5 - 17 February 2019

Please be aware that the pavement outside the Marshall Building development is currently closed.  Please follow the diversion and use the pedestrian crossings to ensure your safety.  Visit the Marshall Building web pages for more information about the project.

19_0090 Lincolns Inn Fields-Closed Pedestrian Route-A1_v1-MAPONLY
Safe pedestrian route along Lincoln's Inn Fields

 

Power to CBR and Open House - October 2018

Centre Buildings Redevelopment (CBR)

The CBR Project Team have been very busy over the Summer months and the exterior of the building is taking shape.  A power supply is now needed to enable the completion of the interior, including state of the art teaching rooms and lecture theatres, ready for Summer 2019.  Unfortunately this will mean circa two weeks of disruptive works on Houghton Street, outside Connaught House commencing 8 October 2018.

The works will involve UK Power Networks (UKPN) excavating a trench from the boundary of the CBR site, along Houghton Street to the Aldwych.  Although best endeavours will be made to control noisy works, there will be breaking and excavation, which will likely cause some disruption to occupants of adjacent buildings.

Apologies for any inconvenience this may cause, if you have any questions or concerns please contact: estates.centrebuildings@lse.ac.uk

Visit the Centre Buildings web page to find out more about the project.

Open House

The Estates Division participated in Open House weekend, showcasing the Saw Swee Hock Student Centre on Sunday 23 September.

212 members of the public were given guided tours of the building by members of the project team with another 100 people taking the self-guided tours. 

Look out for a behind the scenes tour of Centre Buildings as part of Open House 2019.

Summer 2018 update

Resource Booker Update

Room Bookings have recently upgraded Resource Booker (the online room booking portal) and it now allows users to edit their own bookings, and book ahead through to the end of next academic year, in certain categories of rooms.

If you've made a booking in Resource Booker and you now need to change the title, or the running time, or even the date, you can now edit your own bookings in Resource Booker. Simply open the booking in your My Bookings page and click on the Edit button, this will bring up the booking form where you make your changes. Please note that if you edit a booking, it needs to go through Room Bookings' approval process again, so an Accepted (or confirmed) booking goes back to being 'Requested' (or provisional).

If you want to book a catering venue for a reception in November 2018, a small study room for an office hour in October or a meeting room for a committee in May 2019, you can do it now online in Resource Booker. You can also now request bookings in teaching rooms for dates from now up to the end of Welcome week (Friday 28th September). Once the teaching Timetable is completed, and we've processed the advance booking requests you've already sent to Room Bookings, we'll open up bookings on Resource Booker in the teaching rooms in term time for the whole of the Academic year. Keep checking details of what is available to book on the Resource Booker login page.   If you’re planning further ahead or considering hosting an academic conference, have a look at Information on-line  and get in touch via lse.roombookings@lse.ac.uk  to discuss the most suitable time periods for hosting large events on campus.

You can access the Resource Booker How To guide via this link Request a Room Booking which will help you get started in Resource Booker and show you how to edit your bookings.

We hope you find these enhancements useful
The Room Bookings Team

Estates gain another ISO Standard

The Estates Division are delighted to have recently achieved ISO 9001 Quality Management System accreditation.  During two external audits the Estates Division has demonstrated its ability to consistently provide products and services that meet customer and applicable statutory and regulatory requirements, whilst aiming to enhance customer satisfaction through the application of continuous improvement processes.  Only 2 other Russell Group Universities hold this standard across all Estates services.  We welcome your feedback on our services at any time, please email estates.admin@lse.ac.uk with your comments

Reprographics are back!

We are pleased to welcome the Reprographics team back to the Estates ‘family’.  After a period of reporting to IMT, Simon and the team are again part of the Estates FM team, services remain unchanged.  See our about us page for more information on organisational structure.

Development on Campus - update May 2018

The campus and immediate surrounding areas are currently experiencing ongoing development works from four active construction sites:

LSE sites:

  • Centre Buildings Redevelopment - CBR (Mace) on Houghton Street on the West
  • The Marshall Building - MAR (44LIF) (McGee) on the North West

Neighbouring sites:

  • Lodha (Multiplex) on Searle Street on the East (Behind the LSE Library
  • Royal College of Surgeons (Wates) on the North

Of the four projects listed above only the CBR and MAR projects are under LSE control, managed by the Capital Development team within the Estates Division. The LSE Capital Development team liaise on a monthly basis with the contracting team from the other major projects and while we cannot exert any additional control we can confirm that both projects are following the WCC guidelines in relation to noise, dust and general disruption.

Read more about the recent noise mitigation measures carried out by MAR demolition contractor McGee and pre-exam audibility tests on the CBR site.

Traffic and pedestrian management - May 2018

In June 2017 the site vehicle and pedestrian movements were altered to deliver a safer environment for pedestrians and vehicles.

Very few routes needed to be altered however the footpath directly around the MAR site on Portsmouth Street and Portugal Street was closed to allow the site security hoarding to be erected.  This will now remain closed until the project is completed in 2021.  Pedestrians have been diverted onto the footpath on the opposite side of the road by the SU Shop.

The Portugal Street entrance into 32 Lincoln’s Inn Fields (32L) was also closed as a pedestrian safety measure.  Further studies will now be done by Estates in conjunction with 32L occupants to determine how much longer the entrance should remain closed. 

In the next few weeks, it is planned to install a new gantry over the 44 LIF pavement for the next stage of works requiring materials to be loaded onto lorries over the pavement. The gantry will allow pedestrians to pass underneath it safely within a protected enclosure and will be constructed over a weekend. 

Pedestrian diversions have been managed using:

  • Signage at key points;
  • Barriers to guide pedestrians to keep to safe areas
  • MAR and CBR site staff monitor and manage site traffic and ensure safe pedestrian crossing points during working hours.

 

Pedestrian diversion 02
Pedestrian diversion in Portsmouth Street

 

All other pedestrian routes and roads have remained open.  We will be monitoring safety during the course of the works and will notify you of any changes in future newsletters.

Sheffield Street temporary closure March 2018

Tuesday 27 - Friday 30 March  2018*

Most of Sheffield Street will be closed from 27 March for a period of approximately 3 days, due to works taking place on the roof parapet of SAW. *The works are weather dependent, therefore the closure may remain in place for longer if weather conditions prevent the contractor from working.

Access to Parish Hall, Sheffield Street and Portsmouth Street buildings, including the shops, will not be affected.

The Main Entrance to Saw Swee Hock Student Centre will be closed and access to the building will be via the Three Tuns Bar.  Staff and students are encouraged not to enter SAW, unless necessary.

Temporary fire safety arrangements

Due to the above closure a temporary fire assembly point for Connaught House, Cowdray House, Lakatos Building, Lionel Robbins Building and Old Building will be relocated to Lincoln’s Inn Fields. 

If you have any questions about the works or the temporary arrangements, please contact Barbara Moldawa b.moldawa@lse.ac.uk

Centre Buildings project - Increase in construction noise - January 2018

Tuesday 30 January 2018

Mace are currently making some alterations to the concrete tower that has been constructed adjacent to New Inn Passage and Columbia House. These adaptations require the use of handheld pneumatic breakers and this is causing an increase in noise levels being experienced within the Columbia House area. It is likely that these works will take until Tuesday 6 February 2018.

Acoustic quilts are being installed around the scaffold platform while they are undertaking these works in order to reduce the noise.

During this period noisy works are only permitted between the below times:

  • 7:30am-10am
  • 12pm-2pm
  • 4:30pm-6pm

Noise monitors situated on Connaught House and Aldwych House will ensure the contractor is complying with the above.

Find out more about the project. 

Any questions or concerns should be directed to estates.centrebuildings@lse.ac.uk