Estates News Updates

Cheng Kin Ku Building electrical issue - latest updates

 The Chenk Kin Ku Building (CKK) is currently closed, due to an electrical issue which LSE is urgently investigating. Below you can find the latest updates to the School community. 


4pm, 25 March 2025

The Cheng Kin Ku (CKK) Building will be open only for teaching and learning activities from 26-28 March.  

This means that the building will not be accessible for work, study, meeting rooms, or events. Department facilities located in CKK will be closed for the remainder of the week, though academics can collect items from office spaces, noting the limitations outlined below. Staff who need to be on campus can work from dedicated spaces on floor 5 of the Library (LRB) and students can access a variety of study spaces in other LSE buildings.

Further to this, if you do have teaching and learning activities scheduled to take place in CKK, please continue to check your LSE email regularly for potential short-notice changes.

Read the full update

Previous updates:


 

 

Planned closure - Lionel Robbins Building (Library) Saturday 5 April 2025

LSE Capital Development is undertaking a programme of work to accelerate our carbon reduction targets. Work is scheduled in the Lionel Robbins Building (LRB) between June and November 2025 to remove gas boilers and install electric Air Source Heat Pumps. 

Power shutdowns may be required between July and August as the UK Power Networks transformer is upgraded.

An early power shut down is planned for Saturday 5th April, when LRB will be closed from 7am to 12pm (mid-day). This means the Library will be closed to all users between those times.  The shut down is required for design development.

For more information on LSE’s approach to reducing our carbon footprint

Clement's Inn - restricted access during road closure

These works were completed earlier than planned.
The route is now fully accessible and the fire assembly point for Clement House occupants will revert to outside PAN/FAW in Clement's Inn with effect from Monday 24 March 2025.

Access into Clement’s Inn from the Strand/Aldwych will be restricted from Monday 3 March to 28 March. Pedestrian access should be unaffected, this is due to gas works on the Strand. 

During this period the fire assembly point for Clement House occupants will be outside the Garrick as shown on the map (pdf).

|Campus map showing temporary fire assembly point for Clement House 3-28 March 2025

LSE Estates Division achieves Gold

The LSE Estates Division have achieved the ‘We invest in people Gold’ accreditation.

This incredible accomplishment is a direct result of everyone’s hard work and dedication.  The Investors in People assessment recognized this, and we're thrilled with this achievement.

It's a significant milestone, as only 28% of organisations achieve Gold accreditation, highlighting our strong culture of mutual support and commitment to making our workplace even better.  We're especially proud to be one of only two University Estates Departments in the UK to hold this prestigious recognition.

The We invest in people assessment gave us valuable feedback, we were especially delighted to hear that the vast majority of our people feel respected, valued and appreciated for the work they do. We're committed to continuous improvement and are using the feedback to develop recommendations and an action plan to drive further positive changes and keep moving forward.

Julian Robinson, Director of Estates added

“We are LSE’s largest Service Division with the most diverse staff who are valued by the School community. We are only as good as the people we employ and to have achieved this gold standard makes me incredibly proud. It is my privilege to lead this amazing team! Thank you to all Estates staff for the great work they do and to those who took part in the survey and interviews with the assessor and especially to Allan Blair, Jas Sidhu and Davinder Ratra for steering us through the very tough assessment." 

IiP Gold Plaque
We invest in people Gold plaque

Road closure during Graduation ceremonies 16 - 19 December 2024

Portugal Street will be closed to traffic for the duration of the Graduation ceremonies 16 - 19 December 2024 from 8am to 8pm.

Please see the traffic management plan detailing the diversion route below. 

Diversion Route Plan - Portugal Street Graduation 2024
Map showing road closure

Please note, there will be limited access to Gorger Alley and a parking bay suspension on Portugal Street (Beside Peacock Theatre).

Campus Longitudinal Study on Students’ Views of the Estate

What do students think about the Estate? Evolving LSE's campus to meet students' needs

Studies on student perceptions of campus quality were undertaken in 2011, 2015, 2019 and 2023, and in 2012 research on what student aspirations for campus study space, were undertaken. Find out how the School addressed the complex challenge of evolving the campus to meet students' wants and needs.

Campus cycle rack survey

As part of the Bankside House redevelopment planning application we are required to undertake a survey of the usage of cycle racks on campus.  This will involve installing temporary cameras that will monitor usage of all campus cycle storage for approximately one week.

The cameras will be installed on Thursday 28 November and removed on Friday 6 December 2024.  Signage will be installed at each point to make everyone aware of the cameras and their purpose.

If you have any questions please contact Stuart Pennycook at: s.pennycook@lse.ac.uk

King's Chambers finial works

These works will not commence on 28 October, as planned.  Once a start date has been agreed this will be communicated.  Apologies for any inconvenience.

George IV envelope remedial works 29 July - December 2024

Essential roofing and building fabric work to George IV Building will commence on 29 July 2024. Due to unforseen works during construction, the completion date will now be 13 December 2024.

To ensure the safety of students and staff passing through this area, the contractor will put out safety barriers around the working area when they are putting up and taking down the scaffolding.

George IV Pub will continue trading throughout the construction programme and their opening hours will not be affected by the construction works.

George IV Building Envelope 2024
Map of scaffold enclosure

We apologise for any inconvenience caused during these essential maintenance works.

If you have any further queries or problems, please contact: d.mcpherson1@lse.ac.uk 

Temporary diversion on Clement's Inn 8 - 12 July 2024

Due to roof works at 265 Strand, Clement's Inn will close at Strand end (access will be via CBG steps) 8 - 11 July (4pm-10pm) and possibly 12 July, 4pm-10pm (if weather delays occur).

Please use the alternative route during this time:

Clements Inn Route closure map with assembly June July 2024
Alternative route to/from Clement's Inn during closure period

The fire assembly point for Clement House occupants will be outside the Garrick during this time. 

Decarbonisation project to commence in LRB and CON

Back in February 2024, LSE received £2.7m of funding from Salix.  As reported, these funds will be used to take a whole building retrofit approach to the decarbonisation of two campus buildings: Connaught House (CON) and Lionel Robbins Building (LRB).

Find out more about the project that will start soon and is estimated to complete in Winter 2025. 

Old Curiosity Shop wins RICS award

The Old Curiosity Shop has been awarded winner in the RICS Regional Awards 2024 category of Heritage Project for the London region.  The project was one of 9 London projects shortlisted for the regional award. 
Congratulations to Barbara Moldawa from our Capital Development team, who led the project for LSE Estates.
Read more about the awards here

 

Old Curiosity Shop
RICS Certificate awarded to The Old Curiosity Shop

Lincoln's Inn Fields road closure Sat 8 - Sun 9 June 2024

A tower crane is due to be installed at 35 Lincoln’s Inn Fields (elevation facing the Sir Arthur Lewis Building, SAL) on the weekend of 8 – 9 June 2024 which will involve a road closure to part of Lincoln Inn Fields (LIF). The map below illustrates the extent of the roads and parking bays that will be affected during the erection of the tower crane. Notices have been posted on lampposts in the area advising of the road closures.

Road closure LIF June 2024
Plan showing closures during tower crane lift

The closures will commence on Saturday 8 June from 6:00am and roads will reopen on Sunday 9 June at 8.00pm. The contractor has provided the following programme of activities for the weekend.

Description

Start

Date

Finish

Date

Road closure of LIF between Serle Street and Portsmouth Street

6am

08/06/24

8pm

09/06/24

Parking bays on LIF adjacent to 35 Lincoln Inn Fields suspended

6am

08/06/24

8pm

09/06/24

Mobile crane in place to prepare for the tower crane installation

8am

08/06/24

10am

08/06/24

Tower crane delivered in 9 sections throughout the day on the back of articulated lorries

10am

08/06/24

1pm

09/06/24

Tower crane installation

10am

08/06/24

1pm

09/06/24

Read more about the Firoz Lalji Global Hub Redevelopment Project and, more specifically, find out how the demolition works may impact you.

Temporary diversion on Clement's Inn 6 May - 3 June 2024

Due to scaffolding removal at 265 Strand, Clement's Inn will close each evening from 5-11pm (6-11pm during exams in CLM and PAN) from 6 May - 3 June 2024.

Please use the alternative route during this time:

The fire assembly point for Clement House occupants will be outside the Garrick during this time. 

Clements Inn Route closure map with assembly 2024
Map shows alternative route during closure of Clement's Inn